US · structure · take-off and pre-sizing
How much concrete, steel and brick does this take?
Two questions travel together on any structural element: how big does it have to be, and how much material does that mean. This runs both. Give the span, the load and the soil, pick the element, and you get the dimension a preliminary sizing rule produces plus the cubic yards, bags, pounds of rebar and brick count that follow from it.
Cubic yards · premix bags · lb of rebar · brick count Presumptive soil bearing per IBC Table 1806.2 5 calculators inside
Your situation
Which element are you working on?
Preliminary sizing rules and material take-offs. The dimensions you enter carry across all five, so you can walk the whole structure without retyping.
That's not my case
Fine-tune the estimate
The element
Feet for length and span, inches for section, pounds for load. Only the fields your branch uses affect the answer.
Footing run for a strip footing, clear span for a beam.
Footing width. The beam branch derives its own width from the depth.
Footing depth, or slab thickness for the rebar branch.
Unfactored load arriving at the top of the footing. 40,000 lb is a typical two-story interior column.
IBC Table 1806.2 presumptive values: 1,500 clay · 2,000 silty or clayey sand · 3,000 sandy gravel.
Used by the rebar and masonry branches. Wall area is face area, openings already subtracted.
Sets the reinforcement ratio range used for the steel weight.
Sets the units per square foot and the unit weight.
5 to 10% is normal. Go higher on a job with many cuts or a difficult delivery.
Preliminary estimate. It does not replace structural calculations, technical documents, or supervision by a licensed professional.
How the total adds up
From dimensions to the delivery ticket
Sizing first, then volume, then the units the supplier actually sells: cubic yards, bags, pounds and pieces.
Structural quantities are easiest to sanity-check by weight: it is what the truck carries, what the crane lifts and what the footing underneath has to hold. The split shows the cement, the aggregate and water, the reinforcing steel and the masonry and mortar that make up the element.
Quick answer
What applies to you
What's included
Watch out for this
Deadline:
Frequently asked questions
How many cubic yards of concrete do I need?
Multiply length, width and depth in feet to get cubic feet, then divide by 27. The trap is mixing units: a footing 20 feet long, 24 inches wide and 12 inches deep is 20 × 2 × 1 = 40 cubic feet, which is 1.48 cubic yards, not 480 of anything. Ready-mix is ordered in quarter-yard steps and almost always carries a short-load charge below about 3 yards, so round up rather than risk a second truck.
When should I bag-mix instead of ordering ready-mix?
An 80 lb bag yields about 0.60 cubic feet, so a cubic yard takes 45 bags — roughly 3,600 pounds you have to carry, open and mix. Below about a quarter yard (12 bags) bag mixing is clearly right. Above half a yard it becomes a long, hot day with an uneven result, because bag-to-bag water content varies and cold joints form while you mix the next batch. Anything structural and continuous should be one pour from one source.
What soil bearing pressure should I assume?
If you have a geotechnical report, use its number and nothing else. Without one, IBC Table 1806.2 gives presumptive values: 1,500 psf for clay and silty clay, 2,000 psf for sandy silt and clayey sand, 3,000 psf for sandy gravel and gravel, and 12,000 psf for crystalline bedrock. This calculator defaults to 2,000 psf. Note that presumptive values assume undisturbed natural soil — engineered fill, organic soil and expansive clay all fall outside the table and need testing.
How big does a spread footing under a column need to be?
For bearing, divide the service load by the allowable soil pressure and take the square root for a square footing. A 40,000 lb column on 2,000 psf soil needs 20 square feet, so about 4 ft 6 in square. That is only the bearing check: the footing also has to be thick enough to resist punching shear around the column, and reinforced for the bending it sees as a cantilever off the column face. Those two usually set the thickness, and they are engineer territory.
How deep should a concrete beam be?
The traditional first pass is span over twelve for depth and half of that for width. In imperial units it is memorable: depth in inches equals the clear span in feet, so a 20 ft span starts at a 20 by 10 in beam. Treat that as a placeholder for coordination, not a design. Deflection limits, concentrated loads, continuity over supports and the space the reinforcement actually needs all push the real number around, sometimes by a lot.
How much rebar goes into a slab?
As a budgeting figure, a solid reinforced slab carries 2.0 to 3.1 pounds of steel per square foot, a joist-and-block slab 1.4 to 2.0, and a lightweight or voided slab 1.6 to 2.5. A 400 square foot solid slab therefore lands between 820 and 1,230 pounds of steel. Add 5 to 10% for laps and offcuts. These ratios are useful for pricing and for checking that a supplier quote is in the right universe; they are not a bar schedule.
How many bricks are in a square foot of wall?
A modular clay brick with standard 3/8 inch joints gives 6.86 units per square foot of single-wythe wall — the figure the Brick Industry Association publishes and every US supplier quotes. Queen size gives 5.76, utility brick 3.0, and an 8 by 8 by 16 inch concrete block 1.125. A double-wythe solid brick wall is two leaves, so about 13.7 per square foot of face. Add 5 to 10% for breakage and cuts on top of any of them.
How much mortar does a brick wall take?
About 7 cubic feet of mortar per thousand modular brick with standard joints, which is roughly 875 pounds of wet mortar. Concrete block takes less per square foot of wall because there are fewer, larger joints, but the joints themselves are thicker. Waste is high with mortar — what boards up, what stiffens past working time, and what falls — so 10 to 15% over the theoretical figure is normal on a real wall.
What does a masonry wall weigh?
A single wythe of modular brick runs about 35 to 40 pounds per square foot of face including mortar; a double-wythe wall is over 60; an 8 inch hollow concrete block wall about 38 to 55 depending on whether the cores are grouted. That number matters twice: the footing has to carry it, and on a retrofit the existing structure may not have been sized for it. Swapping a stud wall for a masonry one without checking the foundation is a classic and expensive mistake.
Do I need a permit and an engineer for this work?
Almost always for anything structural. Footings, beams, retaining walls and load-bearing masonry are permitted work in essentially every US jurisdiction, and most require sealed drawings from a licensed engineer or architect. The inspection sequence matters too — footing excavations and reinforcement are typically inspected before the pour, and concrete placed before that inspection can be ordered removed. Check with the local building department before excavating, not after.
How do the metric values in the original formulas convert?
The conversions used here are: 1 cubic meter is 35.31 cubic feet or 1.308 cubic yards; concrete at 2,400 kg per cubic meter is 150 pounds per cubic foot; 1 kg per square meter of reinforcement is 0.2048 pounds per square foot; and 150 kN per square meter of soil bearing is 3,133 psf. Where a metric source constant and a published US figure disagree — as they do slightly on bricks per unit area — this calculator uses the US figure and shows the metric one alongside it.
Why does the cement content look high compared to a normal mix?
Because the underlying rule of thumb this calculator ports assumes ten 50 kg sacks of cement per cubic meter, which is 500 kg per cubic meter or 31.2 pounds per cubic foot. That is a rich site mix aimed at small hand-batched footings where compaction is poor. Structural ready-mix is typically proportioned at 300 to 350 kg per cubic meter and reaches higher strength with less cement because it is properly graded, dosed and vibrated. If you are ordering ready-mix, specify a strength class and let the plant proportion it.